Cannon and Surrounding Roadway Construction Update

Comment   Email   Print
Related Articles

CANNON COUNTY SR-1 (US-70S) installation of a flashing beacon at the intersection of SR-281 (Center Hill Road, LM 12.4): The contractor is scheduled to begin construction on 02/06/23. The contractor will be utilizing right lane closures through the work zone once work starts. Motorists should use caution through the work zone and watch for flaggers that may be present.

[Stansell Electric Company, Inc./Harris/CNW229]



CANNON AND WARREN COUNTY SR-1 (US-70S) bridge repair and paving from east of Lincoln Lane (LM 11) in Cannon County to Robinson Road (LM 9.4) in Warren County: The contractor may utilize short term lane closures and flagging operations to complete any remaining work. Motorists should use caution through the work zone and watch for flaggers.

[American Pavements, Inc./Harris/CNV075]


DEKALB COUNTY SR-26 (US-70) grading, drainage, and construction of retaining walls and paving from near SR-53 (LM 2) to near SR-96 (LM 6.1): The contractor continues grading activities throughout the project. Temporary lane closures and/or periodic traffic stoppages will be necessary for construction activities. Motorists are encouraged to use caution while traveling through the work zone and be aware of construction personnel.

[Twin K Construction/Moore/CNV012]



DEKALB AND WARREN COUNTY SR-56 construction of bridges and paving from south of Warren-Dekalb County line (LM 24.5) to East Bryant St. (LM 2.9): The contractor is utilizing flagging operations throughout the project in multiple areas for grading and paving operations. Motorists are now utilizing all new alignment for SR-56. Motorists should use caution at the intersections of SR-56 and all side roads through the project, as these intersections have changed recently. Motorists traveling old SR-56 should use South Tittsworth and the newly constructed Turner Road to access the new alignment of SR-56. Work will be on-going near College Street and Douglas Road to complete grade work. The speed limit has been reduced to 45 mph through the construction zone. Motorists should expect delays, watch for flaggers, and use caution when traveling through the work zone.

[Jones Bros. Contractors, LLC/Harris/CNT011]

RUTHERFORD COUNTY I-840 / I-24
On-call concrete repair
Continuous, the exit ramp from I-840 EB to I-24 EB (Exit 53A) will be narrowed and traffic shifted to repair damaged concrete.

RUTHERFORD COUNTY I-24
The resurfacing of I-24 from E of Epps Mill Road to Beechgrove
Nightly, 8 p.m. - 5 a.m., There will be alternating lane closures re-stripe painted pavement markings.

RUTHERFORD COUNTY SR 1
LPLM: Town of Smyrna Street Scapes on SR-1
Daily, 9 a.m. - 3 p.m., There will be alternating lane closures for construction activities.

RUTHERFORD COUNTY SR 99
The grading, drainage, construction of retaining walls, signals and paving on SR-99 (New Salem Hwy) from near I-24 to SR-96 (Old Fort Pkwy)
Daily, 9 a.m. - 3 p.m., There will be periodic flagging operations for construction activities. Industrial Blvd will be closed on Sat 2/4. A signed detour will be in place.

RUTHERFORD COUNTY SR 266
The grading, drainage, construction of two concrete bulb tee beam bridges, signals, and paving on SR-266 (Jefferson Pike) from SR-102 (LM 5.0) to E. of I-840 (LM 9).
Daily, 9 a.m. - 3 p.m., There will be periodic flagging operations for construction activities.

Read more from:
COURIER SPOTLIGHT
Tags: 
None
Share: 
Comment   Email   Print
Powered by Bondware
News Publishing Software

The browser you are using is outdated!

You may not be getting all you can out of your browsing experience
and may be open to security risks!

Consider upgrading to the latest version of your browser or choose on below: